case · [2012] EWHC 1773 (TCC)

Where the time went, and what it cost.

Three houses in London SW5, a JCT contract let before the design was done, and a four-year argument over time and money. The film follows the judgment from the contractor's notices to the sums the court allowed.

75 seconds · silent · captionedRead the judgment
The case

The case on one sheet

Scheme
Three adjacent houses in London SW5; the dispute concerns one of them
¶4 · ¶17
Contract
JCT Standard Form 1998, Private Without Quantities, with Contractor's Designed Portion
¶102
Contract sum
£5.28M for the house in dispute
¶17
Liquidated damages
£2,150 to £6,400 a day, graded
¶11
Parties
Walter Lilly & Co (contractor) · DMW Developments (employer) · BLDA (architect and contract administrator) · Gardiner & Theobald (quantity surveyor)
¶1 · ¶6
The start
Design work was nowhere near complete when the contractor was appointed, and all the building works were provisional sums
¶1 · ¶13
PROGRAMME AND DISPUTE20042005200620072008200920102011201280 WEEKS PLANNED208 WEEKS TO COMPLETE128 WEEKS LATE · DERIVEDPOSSESSIONJUL 04COMPLETION DUEJAN 06LDs DEDUCTEDFEB 07PRACTICAL COMPLETIONJUL 08PROCEEDINGSMAR 10JUDGMENTJUL 12CONSTRUCTION INTELLIGENCE GRAPH
Decided

What the court decided

Time · clause 25
“where delay is caused by two or more effective causes, one of which entitles the Contractor to an extension of time as being a Relevant Event, the Contractor is entitled to a full extension of time”¶370

Two causes, one of them a Relevant Event: the contractor gets the full extension. No apportionment.

The court found a full extension to practical completion, 7 July 2008. ¶459

Money
Loss and expense · clause 26¶461 · ¶539
Claimed by the contractor
£1,429,177
Offered by the employer
£68,340.80
Allowed by the court
£860,714
Liquidated damages¶655 · ¶658
Withheld for delay and defects
£854,596
Liquidated damages allowed
£0
Net due to the contractor
before interest · ¶658
£2,330,666
The graph

The graph behind the film

The film's graph scenes come from the judgment read as a graph, each item tied to the paragraph it came from. We show the live graph in a walkthrough.

  • Letters and notices
  • Events on site
  • Claims
  • Contract clauses
  • The court's decisions

Walter Lilly, [2012] EWHC 1773 (TCC), on Find Case Law. Contains information licensed under the Open Justice Licence v2.0.

Figures are the judgment's, with paragraph references; derived figures are marked. People are not named.